Skip to main content

Everything new in Rudolfinerhaus!

Sun, 01.11.2020

After a multi-stage renovation the project "Adaptation and Extension of Rudolfinerhaus" was completed in autumn 2020. Five new wards were put into operation in the private hospital in Vienna-Döbling with a total of 80 patient-friendly single rooms with sunny loggias and terraces. The clinic also opened the new Wilczek Pavilion and the Rudolfinerhaus Campus for health and nursing education.

In the first construction stage (February 2018 - March 2019) the Billroth Pavilion was heightened and rehabilitated and in this connection 37 new patient rooms were erected.

The second construction stage with a construction period of 15 months (July2019 - September 2020) comprised the redesign of the forecourt and the entrance area of the Rudolfinerhaus private hospital. A generous and barrier-free access to the building for picking up and dropping off patients was created and the subterranean garage was linked to the building by erecting porches. The entrance and foyer area was modernized and reconstructed to an attractive area thanks to a new light-flooded design. Parallel to the construction measures on the forecourt the partial demolition of the Wilczek Pavilion and the new erection of the pavilion with southern side patient rooms as well as the extension of the attic for the teaching programme on the Campus started at the beginning of July 2019.

Client. Rudolfiner-Verein Rotes Kreuz

Services. Site supervision, health and safety engineering, electrical and HVACR design

Beteiligtes CC. CC Site Supervision

Rudolfinerhaus © Toni Rappersberger
© Toni Rappersberger
Rudolfinerhaus © Toni Rappersberger